ERP integration

The project in APplus, staff scheduling through to acceptance in Linetrack.

In APplus an order can be run as a project from the quotation stage onwards. Linetrack takes over its structure and plans who designs, pre-assembles and commissions at the customer's site and when, own fitters as well as subcontractors. Through the REST API the project, staff and suppliers come from APplus, and dates, planned hours and schedule adherence go back.

Via the REST APIProject structure from APplusFitters and external staffDates back to the ERP

APplus website ↗

In short

APplus by Asseco Solutions is connected through the Linetrack REST API, set up via APplus interfaces, your APplus partner or middleware such as Power Automate, Make or n8n. From APplus, Linetrack takes projects with structure, tasks and dependencies, employees by personnel number, and customers and suppliers as project partners. The dates of tasks and milestones, planned hours per task and resource, and KPIs such as schedule adherence and time progress go back to APplus.

What is transferred

Structure, staff, partners: what comes from APplus

In plant engineering the delivery date depends on assembly. That is why, besides the project, Linetrack takes the people and companies working on it from APplus and reports back when what will be finished.

To LinetrackFull plan

Project structure from APplus

If the project is already structured in APplus, the structure comes to Linetrack in full: up to 2000 tasks across up to 20 levels, with milestones such as FAT, shipment and SAT and the dependencies between them. Every task keeps its ID from APplus.

  • Project number
  • Tasks
  • Milestones
  • Levels
  • Dependencies
  • Lag
  • APplus ID

Where in Linetrack: the project Gantt

To LinetrackSubtree

Assembly planning as detailed planning

When installation at the customer's site is planned in more detail later, the interface sends this part as one list under the task “Assembly”. Linetrack replaces only this subtree; design and production in the rest of the plan stay as they are.

  • Source ID
  • Tasks
  • Milestones
  • Dates

Where in Linetrack: under the task in the Gantt

To LinetrackStaff

Own fitters and designers

The sync creates and updates employees by personnel number. Anyone missing from a delivery from APplus stays in Linetrack. Absences come with their type, so holidays and training reduce the available time.

  • Personnel number
  • Short code
  • Holiday
  • Sickness
  • Training
  • Assembly

Where in Linetrack: resource view

To LinetrackResources

External fitters and bottleneck machines

Subcontractors for piping or electrical installation and bottlenecks such as the paint booth or test bench are created by the interface as virtual resources. They can be assigned to tasks like your own employees and appear in the same resource view.

  • Virtual resource
  • Short code
  • Resource group
  • External staff
To LinetrackPartners

Customer, suppliers, subcontractors

Customer and suppliers come from the APplus master data as project partners with ERP number and contacts. On the project, the assembly manager sees which companies are involved and who there is responsible for the plant.

  • Customer
  • Supplier
  • Supplier number
  • Contacts
  • Project assignment

Where in Linetrack: project partners

BackDates

Dates and schedule adherence for APplus

APplus reads the current dates of tasks and milestones from Linetrack, the planned hours per task and resource, and KPIs per project with schedule adherence and time progress. If the SAT moves, the new date is also on the project in APplus.

  • Start
  • Finish
  • Milestones
  • Planned hours
  • Schedule adherence
  • Time progress
  • Phase

In plant engineering

From pre-assembly in the works to acceptance on site

The filling line is pre-assembled in the works

The project is structured in APplus. Linetrack takes over tasks, milestones and dependencies, and the project manager assigns pre-assembly and wiring to the people who are actually in the building in May. Holidays and training from the sync are already deducted.

A subcontractor for the piping

For installation at the customer's site a piping subcontractor joins the project. It is a project partner with a contact person on the project, and its fitters are virtual resources in the plan. The assembly manager sees whether own electricians and external fitters are on site in the same week.

The customer moves the SAT

The customer's building is not ready in time and acceptance moves by two weeks. The project manager pushes the milestone back in Linetrack and replans commissioning. On the next fetch APplus takes over the new date for further order processing.

Process

How the route runs between APplus and Linetrack

  1. 1

    Leading system per field

    APplus owns project number, customer and suppliers; Linetrack owns dates and staff scheduling. We record this with you and your APplus partner before the route is built.

  2. 2

    Map the structure

    The breakdown of the APplus project becomes the task structure in Linetrack, and every item keeps its ID from APplus. Recurring sequences can come from a Linetrack template instead.

  3. 3

    Set up the calls

    An API key with the areas needed, then APplus interfaces, your partner or a middleware call the Linetrack API, on a schedule or when the project changes.

  4. 4

    Check on one project

    During the test phase, the project manager and the person responsible for APplus compare a running project in both systems. Once dates and hours match, the route runs for all new orders.

FAQ

Frequently asked questions

Any questions?

Book a call with our team.

Who builds the connection to APplus?

Your APplus partner or your IT team, optionally with middleware such as Power Automate, Make or n8n. It is based on the documented Linetrack REST API. We agree with you up front which data should flow from APplus.

Does the project structure in APplus have to be complete?

No. Linetrack can create a project from a template with a start date or take over the complete structure from APplus. The two can be combined: the framework from the template, assembly later as detailed planning from the ERP.

Do assemblies or bills of materials come over from APplus?

As a reference, yes; as a bill of materials, no. An assembly or drawing number can sit on the task as a property, as text or a link. Material items and purchase orders stay in APplus.

How do external fitters get into the plan?

As virtual resources, created through the interface or by Excel import. They can be assigned to tasks and appear in the resource view next to your own employees.